Sec. 151.45 - Performance of construction work:
General requirements.
(a) All construction work under a
project must be performed under contract, except in a case where the
Administrator determines that the project, or a part of it, can be more
effectively and economically accomplished on a force account basis by the
sponsor or by another public agency acting for or as agent of the sponsor.
(b) Each contract under a project must
meet the requirements of local law.
(c) No sponsor may issue any change
order under any of its construction contracts or enter into a supplemental
agreement unless three copies of that order or agreement have been sent to
and approved by the Area Manager. §§151.47 and 151.49 apply to
supplemental agreements as well as to original contracts.
(d) This section and §§151.47 through
151.49 do not apply to contracts with the owners of airport hazards, (as
described in §151.39(b)), buildings, pipe lines, power lines, or other
structures or facilities, for installing, extending, changing, removing,
or relocating that structure or facility. However, the sponsor must obtain
the approval of the Area Manager before entering into such a contract.
(e) No sponsor may allow a contractor or
subcontractor to begin work under a project until --
(1) The sponsor has furnished three
conformed copies of the contract to the Area Manager; and
(2) The Area Manager agrees to the
issuance of a notice to proceed with the work to the contractor. However,
the Area Manager does not agree to the issuance of such a notice unless he
is satisfied that adequate replacement housing is available and has been
offered to affected persons, as required for project eligibility by
§151.39(a)(5).
(f) Except when the Area Manager
determines that the sponsor has previously demonstrated satisfactory
engineering and construction supervision and inspection, no sponsor may
allow a contractor or subcontractor to begin work, nor may the sponsor
begin force account work, until the sponsor has notified the Area Manager
in writing that engineering and construction supervision and inspection
have been arranged to insure that construction will conform to FAA
approved plans and specifications, and that the sponsor has caused a
review to be made of the qualifications of personnel who will be
performing such supervision and inspection and is satisfied that they are
qualified to do so.
[Doc. No. 1329, 27 FR 12351, Dec. 13, 1962, as
amended by Amdt. 151-31, 34 FR 4885, Mar. 6, 1969; Amdt. 151-39, 35 FR
5537, Apr. 3, 1970]